The
Executive Governor of Katsina State visited the Danja Earth Dam & Access
Road Construction Project by 2ndJune with his cabinet members.
This is
the first visit after the contract is awarded to MCC and the fully mobilized
and commencement of the project. During his visit the Governor has inspected
the cofa dam which has over 1 million cubic water reservation for the
construction, the dam foundation which has been excavated and under treatment,
the spill way which is under blasting to excavate the rocks, the quarry for
protection rock, the access road which is fully accessible, the crashing plant
for chippings production, the sand plant and other material production site as
well.
The honorable
commissioner for water resources, the project consultant and MCC site team
reported the progress, the achievement and the challenges the project during
the visit. The Governor finally addressed to all state holders about his
happiness on this visit and appreciated MCC on the quality works and
commitment. He assured MCC and the project monitoring team his best support to
the project to make sure the completion and the commissioning within 2021. Also
he called on MCC to continue the standard on the quality control and make sure
the commissioning target been achieved for the benefit of Katsina People.